Student Health Services will continue to operate at the Health Center
while construction is taking place. Anyone may
go to the Cowell Student Health Center to see a doctor, make an
appointment, or access the pharmacy.
Student
Health and Outreach Programs (SHOP) has relocated to Kresge
College, Rm.157 (across the patio from the college office)
Rape Prevention
Education Program has been relocated to Kresge College, Rm 153.
| This project will address seismic deficiencies by upgrading
the existing structural systems to a seismic performance of "Good". The structural work
will also trigger mandatory accessibility other code improvements. Construction includes
addition of additional space to accommodate current health services offered on campus. |
 |
| Project Completion: |
Fall 2009 |
| Architect: |
Hawley Peterson & Snyder Architects |
| Contractor: |
DPR Construction |
| Project Management: |
Physical Planning & Construction |
Phases of Construction: Demolition and Structural Upgrade
of basement and second floor to begin June 16 and to be completed
by September 22, 2008.
Monday (07/28/08):
- Radar of rebar in 1st & 2nd Floors slabs at gridlines
1, 2A & 5.
- Continue saw-cutting at Basement along gridline 1(mild
intermittent noise)
Tuesday (07/29/08):
- Ongoing lead paint removal in Basement (after 5:00 PM).
- Bushing & drilling concrete in Basement, 1st & 2nd
Floors along gridlines 1, 2A, & 5
(mild intermittent noise)
Wednesday (07/30/08):
- Ongoing Mech / Electrical safe-off and demo at Basement,
1st & 2nd Floors.
- Bushing & drilling concrete in Basement, 1st & 2nd
Floors along gridlines 1, 2A, & 5
(mild intermittent noise).
- Continue saw-cutting in Basement between gridlines F & D2
and along gridline 1.
This work to start at 4 AM and continue throughout day.
Thursday (07/31/08):
- Ongoing coring slabs on 1st & 2nd Floor from gridlines
2A to 5 and K to F (mild
intermittent noise).
- Bushing & drilling concrete in Basement, 1st & 2nd
Floors along gridlines 1, 2A, & 5
(mild intermittent noise)
Friday (08/01/08):
- Bushing & drilling concrete in Basement, 1st & 2nd
Floors along gridlines 1, 2A, & 5
(mild intermittent noise)
Full schedule since 7/21/2008
UCSC Cowell Health Center - Construction Phasing Plan (Rev. 3)
UCSC
Cowell Health Center - Construction Phasing Plan Update 7/17/08
Bi-weekly staff meetings to address construction progress and issues.
For building Emergencies: 911
Concerning Cowell Student Health services
during construction, contact:
Cowell Student Health Center
(831) 459-2211
Concerning issues with construction, contact:
Josephine L. Ortega,
Architect,
Project Manager, PPC
212-0451 Cell / 459-2152 Direct
ortegajl@ucsc.edu