Phases of Construction: Demolition and Structural Upgrade
of basement and second floor to begin June 16 and to be completed
by September 22, 2008.
Monday (07/21/08):
- Shut-down of supply fan (SF-1) in Basement.
- Continue with concrete slab demolition in Basement (mild intermittent
noise).
- Remove containment on 1st & 2nd Floors
Tuesday (07/22/08):
- Begin lead paint removal in Basement (after 5:00 PM).
- Begin new wall layout on 1st & 2nd Floors.
Wednesday (07/23/08):
- Begin Mechanical Demo / Electrical Safe-off on 1st & 2nd Floors
(mild intermittent
noise).
Thursday (07/24/08):
- Begin core-drilling on 1st & 2nd Floors (mild intermittent
noise).
- Continue Mechanical Demo / Electrical Safe-off on 1st & 2nd Floors
(mild
intermittent noise).
Friday (07/25/08):
- Begin core-drilling on 1st & 2nd Floors (mild intermittent
noise).
Monday (07/28/08):
- Radar of rebar in 1st & 2nd Floors slabs at gridlines
1, 2A & 5.
- Continue saw-cutting at Basement along gridline 1(mild
intermittent noise)
Tuesday (07/29/08):
- Ongoing lead paint removal in Basement (after 5:00 PM).
- Bushing & drilling concrete in Basement, 1st & 2nd
Floors along gridlines 1, 2A, & 5
(mild intermittent noise)
Wednesday (07/30/08):
- Ongoing Mech / Electrical safe-off and demo at Basement,
1st & 2nd Floors.
- Bushing & drilling concrete in Basement, 1st & 2nd
Floors along gridlines 1, 2A, & 5
(mild intermittent noise).
- Continue saw-cutting in Basement between gridlines F & D2
and along gridline 1.
This work to start at 4 AM and continue throughout day.
Thursday (07/31/08):
- Ongoing coring slabs on 1st & 2nd Floor from gridlines
2A to 5 and K to F (mild
intermittent noise).
- Bushing & drilling concrete in Basement, 1st & 2nd
Floors along gridlines 1, 2A, & 5
(mild intermittent noise)
Friday (08/01/08):
- Bushing & drilling concrete in Basement, 1st & 2nd
Floors along gridlines 1, 2A, & 5
(mild intermittent noise)
|