Cowell Student Health Center Seismic Corrections and Renovations



Schedule

Phases of Construction: Demolition and Structural Upgrade of basement and second floor to begin June 16 and to be completed by September 22, 2008.

Monday (07/21/08):

  • Shut-down of supply fan (SF-1) in Basement.
  • Continue with concrete slab demolition in Basement (mild intermittent noise).
  • Remove containment on 1st & 2nd Floors

Tuesday (07/22/08):

  • Begin lead paint removal in Basement (after 5:00 PM).
  • Begin new wall layout on 1st & 2nd Floors.

Wednesday (07/23/08):

  • Begin Mechanical Demo / Electrical Safe-off on 1st & 2nd Floors (mild intermittent
    noise).

Thursday (07/24/08):

  • Begin core-drilling on 1st & 2nd Floors (mild intermittent noise).
  • Continue Mechanical Demo / Electrical Safe-off on 1st & 2nd Floors (mild
    intermittent noise).

Friday (07/25/08):

  • Begin core-drilling on 1st & 2nd Floors (mild intermittent noise).

Monday (07/28/08):

  • Radar of rebar in 1st & 2nd Floors slabs at gridlines 1, 2A & 5.
  • Continue saw-cutting at Basement along gridline 1(mild intermittent noise)

Tuesday (07/29/08):

  • Ongoing lead paint removal in Basement (after 5:00 PM).
  • Bushing & drilling concrete in Basement, 1st & 2nd Floors along gridlines 1, 2A, & 5
    (mild intermittent noise)

Wednesday (07/30/08):

  • Ongoing Mech / Electrical safe-off and demo at Basement, 1st & 2nd Floors.
  • Bushing & drilling concrete in Basement, 1st & 2nd Floors along gridlines 1, 2A, & 5
    (mild intermittent noise).
  • Continue saw-cutting in Basement between gridlines F & D2 and along gridline 1.
    This work to start at 4 AM and continue throughout day.

Thursday (07/31/08):

  • Ongoing coring slabs on 1st & 2nd Floor from gridlines 2A to 5 and K to F (mild
    intermittent noise).
  • Bushing & drilling concrete in Basement, 1st & 2nd Floors along gridlines 1, 2A, & 5
    (mild intermittent noise)

Friday (08/01/08):

  • Bushing & drilling concrete in Basement, 1st & 2nd Floors along gridlines 1, 2A, & 5
    (mild intermittent noise)

 