| This project will address seismic deficiencies by upgrading the
existing structural systems to a seismic performance of "Good".
The structural work will also trigger mandatory accessibility and
Title Nine improvements. |
 |
| Project Completion: |
Spring 2008 |
| Engineer: |
Degenkolb Engineers |
| Contractor: |
Cen-Con |
| Project Management: |
Office of Physical Planning & Construction, UCSC |
Two Phases of Construction: (Project duration approximately
6 months)
- Demolition and Structural Upgrade
- Utilities and Interior Finishes
Including past activities and anticipated activities
| September 10 |
Construction began
|
| September 12 – 21 |
Asbestos Abatement
|
| September 24 – October 1 |
Light
Demolition
|
| October 2 – 26 |
Concrete Floor Demolition
|
| October 18 |
1st Brown Bag Meeting
Find out more about the West Field House Renovation
12:00pm - 1:00pm
College Eight Study Center |
| October 29 – November 21 |
Concrete Pour
|
| November 26 – January 11 |
Structural Framing and Structural Steel
|
| January 14 – February 8 |
Plumbing, HVAC, Fire Sprinkler, Electrical
|
| February 11 – April 21 |
Interior Finishes: Flooring, Tiles, Counters, Paint, …
|
For building emergencies: 911
Concerning project construction, crew, emergency and health/safety
issues, contact
Ryan Andrews
Director, OPERS
Division of Student Affairs
831-459-4743
randrews@ucsc.edu
Concerning on going issues with construction, contact:
Brent Cooley
Industrial Hygiene Manger, UCSC Environmental Health & Safety
459-5394
bcooley@ucsc.edu
Concerning health/safety issues, contact:
Brent Cooley, MS, CIH, CSP
Industrial Hygienist
Environmental Health & Safety, UCSC
831-459-5394
bcooley@ucsc.edu
ehs.ucsc.edu
|
|
|